The first of four nuclear reactors being built by the United Arab Emirates will come online in 2017 and the rest will be fully operational by 2020, CEO of the Emirates Nuclear Energy Corp (ENEC), Mohammed Al Hammadi, said Monday.
"When they become fully operational in 2020, they will generate 25 percent of UAE power needs," Al Hammadi told the 10th Arab Energy Conference in Abu Dhabi taking place at Viceroy Hotel, Yas Island, Abu Dhabi.
He said that 61 percent of the first nuclear reactor has been completed and it is slated to start production in 2017.
Work is underway on the second and third reactors while the site is being prepared for the fourth, he said. The second reactor will come online in 2018, the third the following year and the last in 2020.
Al Hammadi said another five percent of UAE electricity needs will be provided by renewable energy sources by 2020, helping the Gulf state to cut 12 million tonnes of carbon emissions.
In 2009, an international consortium led by the state-run Korea Electric Power Corp won a US$20.4 billion (15.8 billion euro) deal to build four nuclear power plants in Baraka, west of Abu Dhabi.
Source: WAM
GMT 11:07 2017 Monday ,30 January
Egypt experience dailyGMT 20:09 2017 Monday ,23 January
Palestin's ministerGMT 14:14 2017 Saturday ,21 January
Plans returnGMT 11:23 2016 Sunday ,20 November
US climateGMT 14:08 2016 Saturday ,19 November
'We count on your pragmatism'GMT 10:07 2016 Tuesday ,15 November
Iran missile programme 'non-negotiable'GMT 12:57 2016 Monday ,14 November
Tax on US products if Trump scraps Paris climateGMT 17:01 2016 Saturday ,12 November
‘No turning back,’ says head of UN climate talksMaintained and developed by Arabs Today Group SAL.
All rights reserved to Arab Today Media Group 2021 ©
Maintained and developed by Arabs Today Group SAL.
All rights reserved to Arab Today Media Group 2021 ©
Send your comments
Your comment as a visitor